ECG announces six-day power outages in parts of Ashanti Region

The Electricity Company of Ghana (ECG) has announced six days of scheduled power outages in parts of the Ashanti Region from Thursday, November 26, to Tuesday, December 1, to facilitate an upgrade of the Anwomaso-Ridge Bulk Supply Point transmission line.
In a notice issued on Saturday, November 21, ECG said the outages would occur daily between 7:30 a.m. and 5:00 p.m. as the Ghana Grid Company Limited (GRIDCo) undertakes work on the transmission infrastructure.
The project involves replacing the existing 364MVA single-circuit transmission line with a modern double-circuit system rated at 2 x 488MVA, increasing the total transmission capacity to 976MVA.
The upgrade is expected to strengthen electricity transmission capacity and improve power supply reliability in the Ashanti Region.
Other affected areas are parts of Santase, Atonsu Kuwait, Naachia, Sawuah, Aprabon, Adagya, Esereso, Feyiase and Zoomlion, alongside surrounding communities.