GRIDCo restores damaged Aboadze–Anwomaso transmission line after illegal chainsaw operation

The Ghana Grid Company Limited (GRIDCo) has restored the damaged 330kV Aboadze–Anwomaso transmission line following repair works after a tree felled by illegal chainsaw operators fell onto the infrastructure.
In a statement on Thursday, November 26, GRIDCo said the line had been fully restored to operation at about 12:07 p.m. after engineers completed the necessary repairs.
The transmission line was damaged on Wednesday, November 25, when illegal chainsaw operators felled a tree onto it, disrupting electricity transmission and affecting power supply to parts of the Western and Ashanti regions.
The incident forced system operators to reduce electricity supplied to parts of Ashanti and Western Regions due to the unavailability of the transmission line.
Announcing the completion of the repairs, GRIDCo said, “The Ghana Grid Company LTD. (GRIDCo) wishes to inform the general public that we have successfully completed repairs to the damaged 330kV Aboadze–Anwomaso transmission line, which has now been restored to operation.”
The company said the repair works were completed on Thursday, November 26, at approximately 12:07 p.m.
GRIDCo also appealed to the public to help prevent similar incidents by avoiding activities that could endanger electricity transmission infrastructure.
“GRIDCo wishes to use this opportunity to appeal to the general public to help protect critical electricity transmission infrastructure by refraining from illegal chainsaw operations and other activities in the vicinity of transmission lines and associated facilities,” the statement said.
The company further expressed appreciation to consumers who experienced disruptions during the period, saying it valued their “patience, cooperation and understanding”.